MG BGR-TBA (Main gas pipelines Bukhara gas-bearing district Tashkent-Bishkek-Almaty;
The work site, the main sites of the object «Construction of a gas measuring station and a shift settlement at MG» BGR-TBA «372 km» is located 2 km from the border with the Republic of Uzbekistan and is located 285 km south of the regional center of Turkestan, 210 km southwest of Shymkent, 7 km west of the Zhetysai district center.
From the sites of the Geoinformation system and the shift settlement, in the direction to the west, 1.1 km away is the nearest residential village of Baikons (former Communism). The Shardara reservoir is located in the north direction at a distance of 32 km.
The main objective of the project was the construction of a gas measuring station with service complexes, which includes the following sites:
- gas measuring station and water intake site
- shift settlement
- evaporation pond
- crane units.
The construction of a gas measuring station site and a water intake site for drinking water working personnel is being considered.
For landing on the territory, an architectural solution is proposed the operator’s building and the engineering solution consists of:
- a sewage pumping station,
- a satellite antenna,
- a diesel power plant,
- diesel fuel tanks,
- the fire-extinguishing pumping station,
- fire fighting tank,
KTPN and on the territory of the water intake site of the water supply pumping station (Block box),
the ground pavilion above the well (Block box).
The projected site is located in the Zhetysu district, Turkestan region, the Republic of Kazakhstan. The construction site is mostly flat, completely occupied by cotton crops, with relief marks from +259.17 to +259.72, has a rectangular shape, and occupies an area of 0.9960 Ha (the territory of the gas measuring station) and 0.4980 Ha (water intake site) according to the state act, as well as a decision was made in the project to improve the adjacent territory with an area of 0.3236 Ha with parking for 6 cars/places and gazebos.